Sudbury PBC approves $60,624 Vertex extension for Fairbank drainage oversight Sudbury Permanent Building Committee splits 2-2 on applicant Kay Bell and approves $60,624 Vertex drainage oversight contract.
Sudbury PBC narrows Atkinson pool designer field to three firms Sudbury Permanent Building Committee picks three Atkinson Pool design finalists, sets May 23 interviews. Sorensen Partners led the four-member ranking with 15 points, followed by KMA Design and BH+A tied at 11; SocoTech, with three points, was dropped.
Building committee sets June 21 substantial completion for Fairbank renovation Sudbury PBC pushes Fairbank substantial completion to June 21 after arsenic, drainage and Eversource delays.
Building Committee rejects $107,000 door hardware change order at Fairbank Sudbury PBC rejects $106,994 Fairbank door hardware change order, sends scope back to bid.
Sudbury PBC caps Fairbank drainage negotiation at $150,000 in 4-0 vote Sudbury PBC caps Fairbank drainage talks at $150,000 after rejecting $397,000 change order.