Sudbury PBC approves $60,624 Vertex extension for Fairbank drainage oversight
Sudbury Permanent Building Committee splits 2-2 on applicant Kay Bell and approves $60,624 Vertex drainage oversight contract.
Sudbury Permanent Building Committee splits 2-2 on applicant Kay Bell and approves $60,624 Vertex drainage oversight contract.
Sudbury Permanent Building Committee picks three Atkinson Pool design finalists, sets May 23 interviews. Sorensen Partners led the four-member ranking with 15 points, followed by KMA Design and BH+A tied at 11; SocoTech, with three points, was dropped.
Sudbury PBC pushes Fairbank substantial completion to June 21 after arsenic, drainage and Eversource delays.
Sudbury PBC rejects $106,994 Fairbank door hardware change order, sends scope back to bid.
Sudbury PBC caps Fairbank drainage talks at $150,000 after rejecting $397,000 change order.
Sudbury's Permanent Building Committee accepts 45-day delay at new Fairbank Community Center.
Sudbury PBC extends Vertex through Fairbank Community Center completion in $186,278 vote.
Sudbury committee splits 3-2 to finish Fairbank cedar barn door for $16,000. The Permanent Building Committee on Dec. 6 approved Change Proposal 93.1 at $16,080.66 to complete a decorative cedar sliding door at the new Fairbank Community Center, with Co-Chair Elaine L.
Sudbury PBC authorizes $3,000 drainage survey at Fairbank Community Center as ponding raises design questions.
Sudbury PBC locks in Dec. 12 Fairbank completion as Colantonio claim heads to town counsel.