Permanent Building Committee approves $39,066 to expedite Fairbank switchgear Sudbury's Permanent Building Committee approved a $39,066.28 change order to expedite electrical switchgear for the Fairbank Community Center.
PBC authorizes $100,000 to address unforeseen Fairbank soil problems Sudbury PBC authorizes $100,000 to clear trash-laden soil halting Fairbank foundations.
Sudbury PBC endorses geotech compromise to keep Fairbank foundation work moving Sudbury Permanent Building Committee backs geotech compromise on Fairbank to avert foundation delay.
Sudbury PBC recommends $4.5M fire station contract to Construction Dynamics Sudbury committee recommends $4.5 million fire station contract, with ARPA closing an $811,500 gap.
Fire station filed sub-bids come in $390,000 over budget Sudbury's fire station phase one filed sub-bids landed roughly $390,000 over budget ahead of the July 28 general bid opening.