Sudbury building committee advances DPW roof article ahead of solar install Sudbury Permanent Building Committee strips dollar figure from DPW roof article pending design and bids.
Sudbury PBC approves Fairbank change orders and network switches in three unanimous votes Sudbury Permanent Building Committee approves roughly $47,000 in Fairbank change orders and IT purchases. The committee voted 6-0 to approve change proposals CP1 and CP6 totaling $11,597.95, covering out-of-sequence generator pad demolition and an added water-line run required by the water district.
Sudbury PBC approves up to $673,000 for Fairbank kitchen and furniture Sudbury Permanent Building Committee locks in roughly $673,000 in Fairbank equipment orders before 2022 escalation.
Sudbury building committee rejects most of contractor's 91-day Fairbank delay claim Sudbury panel knocks back 55 days of a 91-day contractor delay claim at Fairbank.
Sudbury PBC commits $11,201 from contingency for underground fire station power Sudbury Permanent Building Committee pulls $11,201 from contingency to bury fire station power.